Rooted in Hawaiʻi. Built for participation.
← Back to S. 1020
Read the measure

S. 1020

A bill to require the Federal Energy Regulatory Commission to extend the time period during which licensees are required to commence construction of certain hydropower projects.

Selected version

Public Law· May 12, 2026

Open the official document ↗

This is a particular imported version. Later drafts may change its provisions, and a recorded vote is not automatically linked to this version.

Choose another version

Readable transcription of the selected official document, not a summary. [Underlined: …] and [Struck through: …] describe recognized source typography; they do not independently establish that wording was legally added or deleted. Layout, tables, and other typography may differ; consult the official document for authoritative wording and formatting. This version is not automatically the version considered in a particular vote.

[119th Congress Public Law 90] [From the U.S. Government Publishing Office]

[[Page 140 STAT. 820]]

Public Law 119-90 119th Congress

An Act

To require the Federal Energy Regulatory Commission to extend the time period during which licensees are required to commence construction of certain hydropower projects. <<NOTE: May 11, 2026 - [S. 1020]>>

Be it enacted by the Senate and House of Representatives of the United States of America in Congress assembled, <<NOTE: 16 USC 806 note.>> SECTION 1. EXTENSION OF TIME TO COMMENCE CONSTRUCTION OF CERTAIN HYDROPOWER PROJECTS.

(a) Definition of Covered Project.--In this section, the term ``covered project'' means a hydropower project with respect to which the Federal Energy Regulatory Commission issued a license before March 13, 2020. (b) Authorization of Extension.--Notwithstanding section 13 of the Federal Power Act (16 U.S.C. 806), on the request of a licensee of a covered project, the Federal Energy Regulatory Commission may, after reasonable notice and for good cause shown, extend in accordance with subsection (c) the period during which the licensee is required to commence construction of the covered project for not more than an additional 6 years beyond the 8 years authorized by that section. (c) Period of Extension.--An extension of time to commence construction of a covered project under subsection (b) shall-- (1) consist of not more than 3 consecutive 2-year periods; (2) begin on the date on which the final extension of the period for commencement of construction granted to the licensee under section 13 of the Federal Power Act (16 U.S.C. 806) expires; and (3) end on the date that is not more than 6 years after the latest date to which the Federal Energy Regulatory Commission is authorized to extend the period for commencement of construction under that section.

(d) Reinstatement of Expired License.--If the time period required under section 13 of the Federal Power Act (16 U.S.C. 806) to commence construction of a covered project expires after December 31, 2023, and before the date of enactment of this Act-- (1) the Federal Energy Regulatory Commission may reinstate the license for the applicable project effective as of the date of expiration of the license; and

[[Page 140 STAT. 821]]

(2) the extension authorized under subsection (b) shall take effect on the date of that expiration.

Approved May 11, 2026.

LEGISLATIVE HISTORY--S. 1020 (H.R. 2072): ---------------------------------------------------------------------------

HOUSE REPORTS: No. 119-477 (Comm. on Energy and Commerce) accompanying H.R. 2072. CONGRESSIONAL RECORD: Vol. 171 (2025): July 29, considered and passed Senate. Vol. 172 (2026): Apr. 21, considered and passed House.

<all>

Source: GovInfo (U.S. Government Publishing Office) · Retrieved Nov 8, 2026 · Source document ↗